Crane Meadow Takes Shape: A View from Above

This aerial photograph, taken by Bowdoin Construction in late September, offers a remarkable view of the progress underway at Crane Meadow, across Pleasant Street from IMS’s existing campus. With foundations in place and walls beginning to rise, the new retreat center is taking shape. To get your bearings, look for Pleasant Street and IMS’s existing parking lot along the upper right of the image. Click the expand icon in the upper-right corner of the photo for a closer look.

Let’s take a tour of the site!

In the foreground is the future Meditation Hall, where workers are pouring the concrete floor of its lower level. A green mixer truck feeds concrete into a blue pump truck, which sends it out onto the slab. Look closely near the upper-left corner of the poured concrete and you’ll see the crew at work, guiding the flow and working the concrete into place. This lower level opens directly to the outdoors and will provide space for walking meditation and mindful movement, along with interview rooms. The main Meditation Hall will rise above it.

Moving toward the center of the photograph, you’ll see the beginnings of the three-story residential building, which will contain 60 rooms for retreatants. The tall concrete elevator shaft gives a sense of the building’s eventual height. Because the land slopes, though, the building won’t rise much higher than the administration building when seen from Pleasant Street.

Nearer the road is the administration building, where framing is underway. The lighter wood is interior framing on its lower floor, and the darker, reddish wood marks the floor joists for the level above. That upper level will be at ground level from the main entrance and will house the reception area, dining room, and kitchen. Other spaces will hold laundry and the facilities shop.

At the upper left of the photograph, near the tree line, you can make out the foundations for three teacher-cottage duplexes.

Much has happened since this photograph was taken. The concrete pour has been completed, and crews have erected many more walls on the lower floors of the residential building and the first floor of the administration building. Work on the residential building in particular has moved along quickly. As the walls rise, the outline of the future retreat center is becoming easier to see.

With each passing week, Crane Meadow is taking another step toward becoming a welcoming new home for retreatants and teachers at IMS.

A closer look toward Pleasant Street: The concrete wall in the foreground lines the lower-level corridor leading to the Meditation Hall. Floor joists are in place at left, with additional materials ready for the next phase of construction. IMS’s parking lot and existing campus is visible across the road.